Data centers in Onondaga County, New York: 1 project mapped
The one data center proposed in Onondaga County is Ranalli Super DC's 300-megawatt plan for a 124-acre industrial site at Hencle Boulevard and Oswego Road in Lysander, where the developer already has approval for a warehouse. No formal application has been filed with the town. Lysander's six-month moratorium, adopted unanimously on May 7, 2026, runs to November 7, 2026, and any application would go to the town planning board.
More than 350 residents came to the May 7 meeting to oppose the plan, and a petition against it passed 1,500 signatures, citing wildlife, air and water, home values and the risk that National Grid passes upgrade costs on to customers. Johanna Bock of Citizens for Lysander worries about who would answer for problems if a facility were sold to a shell company: "So we as a community could have issues and we wouldn't have anywhere to go to." Supervisor Kevin Rode said the state's one-year pause on permits for big data centers covers the site because nothing had been filed before it began.
The county cannot ban or pause data centers itself, so towns are acting on their own. By June 2026 DeWitt, Lysander, Manlius, Salina and Van Buren had moratoriums and Skaneateles had banned data centers outright, county Planning Director Troy Waffner told legislators; Clay adopted a one-year moratorium on June 29, 2026, though no data center has been proposed there. The county is paying up to $500,000 for a neutral consultant's study to help towns decide. "This is not a pro-data center study," Waffner said.
Data center projects on record in Onondaga County
Grouped by the town each site sits in. The report above may name projects that have no record here yet.
Lysander1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Ranalli Super DC, LLC Data CenterLysander | Ranalli Super DC, LLC | Proposed | 300 MW |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Moratoriums and bans in effect
Pauses on new data centers covering this area.
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| ManliusTown or city | Moratorium | Jul 9, 2026 | Jul 9, 2027 | Record off site ↗ |
| LysanderTown or city | Moratorium | May 7, 2026 | Nov 7, 2026 | Record off site ↗ |
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.