Home/Mexico/Guanajuato/TERRANOVA San Miguel de Allende
TERRANOVA San Miguel de Allende data center, Guanajuato, Mexico
Av. La Aurora & C. La Canada, Poligono Empresarial, 37884 San Miguel de Allende, Guanajuato, Mexico
Actis (TERRANOVA)·Under construction·announced 2025
TERRANOVA, the data center company the British investor Actis launched in December 2025, said in February 2026 it was building a second Mexican data center in San Miguel de Allende, Guanajuato, for delivery in early 2026. The company's first Mexican site, in the neighboring Queretaro region, went live that same month with 8.12 megawatts of IT capacity, after being designed in two months and built in ten.
Guanajuato's economy ministry told the newspaper AM in September 2026 that two data centers operate in the state, both run by ODATA, in San Miguel de Allende and Apaseo el Grande, and that a third is being built in San Miguel de Allende by a company it could not name under a confidentiality agreement. The ministry did not confirm that TERRANOVA is behind that third project, and TERRANOVA has not said publicly whether its own San Miguel site has opened.
The ministry put the three projects together at $630 million of investment and 200 direct jobs. On August 10, 2026, Governor Libia Dennise Garcia Munoz Ledo opened a new power plant at the same San Miguel de Allende business park, built by Corral Energy for more than $45 million in its first stage, with 60 megawatts of capacity and a 230-kilovolt connection.
ODATA opened its QR04 data center in the same business park in August 2025, designed for 24 megawatts with a first 12-megawatt phase. Its operations director, Carlos Forero, said the company's water use was minimal.
Asked on September 11, 2026 about local concern over water and energy use, the governor said such investments come with their own water treatment, reuse, power plants and substations, so they do not burden the town's supply. The state says any further details, including whether TERRANOVA's own site is complete, will be announced when the companies involved allow it.
The facts on file
- Company
- Actis (TERRANOVA)
- Address
- Av. La Aurora & C. La Canada, Poligono Empresarial, 37884 San Miguel de Allende, Guanajuato, Mexico
- Region
- Guanajuato
- Country
- Mexico
- Status
- Under construction
- Announced
- 2025
- Operating or planned
- 2026
- Record checked
- Sep 16, 2026
Sources
Everything above comes from these. Open one and check it yourself.
- www.datacenterdynamics.com/en/news/terranova-launches-in-mexico-with-its-first-data-center-campus/
- www.am.com.mx/tecnologia/2026/09/13/guanajuato-atrae-630-mdd-en-centros-de-datos-defiende-el-impacto-en-agua-y
- periodicocorreo.com.mx/san-miguel/2025/aug/14/odata-inaugura-su-cuarto-centro-de-datos-en-san-miguel-de-allend
Other projects nearby
Sites we track within 40 km.
- Aligned QR-04 (San Miguel de Allende)listed on the Guanajuato page13 km
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.