Cipher Digital·Proposed·100 MW
Cipher Digital is developing its Stingray data center project on a 250-acre site west of Andrews in Andrews County, Texas, with up to 100 megawatts of power capacity. The company has leased 70 megawatts of critical IT load at the site to AWS and funded the project with an $810 million bond offering.
At a town hall, Cipher described a plan to treat brackish water from a deep aquifer for the facility, and residents questioned water use, electricity demand and noise. Cipher had targeted energization in the second quarter of 2026, but its own investor materials now target rent starting April 1, 2027 for the site's network hall and May 1, 2027 for its data hall.
The facts on file
- Company
- Cipher Digital
- Tenant
- AWS
- Address
- Nelson Rd, Andrews, TX 79714
- County
- Andrews County, Texas
- Country
- United States
- Status
- Proposed
- Power
- 100 MW
- Operating or planned
- 2025
- Record checked
- Sep 17, 2026
Sources
Everything above comes from these. Open one and check it yourself.
- www.datacenterdynamics.com/en/news/cipher-mining-acquires-more-than-500-acres-across-two-sites-in-texas-for-cr
- www.sec.gov/Archives/edgar/data/0001819989/000095010326008635/dp248110_ex9901.htm
- www.yahoo.com/news/us/articles/were-guinea-pigs-incoming-data-042335896.html
- thenextweb.com/news/cipher-digital-810m-junk-bond-amazon-data-center-texas
Moratoriums covering this site
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| TexasState | Moratorium | Aug 3, 2026 | No end date | Record off site ↗ |
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.