Global Data Centers.formerly Florida Data Centers

Home/United States/Texas/Pecos County/CoreWeave Project Horizon (West Texas)

CoreWeave / Poolside project

CoreWeave Project Horizon (West Texas) data center, Pecos County, Texas

568 acres, Longfellow Ranch, Pecos County, TX

CoreWeave / Poolside·Under construction·2,000 MW

The siteImagery: Esri, Maxar

Poolside and CoreWeave are developing the Project Horizon data center on Longfellow Ranch in West Texas. Pecos County commissioners listed a tax abatement for CoreWeave in the Longfellow Renewable Energy Reinvestment Zone on their January 2026 agenda.

The planned campus would span 568 acres and could reach 2 gigawatts of power capacity. CoreWeave is the anchor tenant for a first phase with 250 megawatts under a 15-year lease, expandable to 500 megawatts, with completion expected in early 2027.

The facts on file

Company
CoreWeave / Poolside
Tenant
CoreWeave
Address
568 acres, Longfellow Ranch, Pecos County, TX
County
Pecos County, Texas
Country
United States
Status
Under construction
Power
2,000 MW
On that figure
planned campus total per DCD ('2GW'); first phase 250MW, expandable to 500MW
Operating or planned
2025
Record checked
Sep 29, 2026

Sources

Everything above comes from these. Open one and check it yourself.

Other projects nearby

Sites we track within 40 km.

Moratoriums covering this site

PlaceTypeStartedEnds
TexasState Moratorium Aug 3, 2026 No end date Record off site ↗

Share this

XFacebookText message

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.