CoreWeave Project Horizon (West Texas) data center, Pecos County, Texas
568 acres, Longfellow Ranch, Pecos County, TX
CoreWeave / Poolside·Under construction·2,000 MW
Poolside and CoreWeave are developing the Project Horizon data center on Longfellow Ranch in West Texas. Pecos County commissioners listed a tax abatement for CoreWeave in the Longfellow Renewable Energy Reinvestment Zone on their January 2026 agenda.
The planned campus would span 568 acres and could reach 2 gigawatts of power capacity. CoreWeave is the anchor tenant for a first phase with 250 megawatts under a 15-year lease, expandable to 500 megawatts, with completion expected in early 2027.
The facts on file
- Company
- CoreWeave / Poolside
- Tenant
- CoreWeave
- Address
- 568 acres, Longfellow Ranch, Pecos County, TX
- County
- Pecos County, Texas
- Country
- United States
- Status
- Under construction
- Power
- 2,000 MW
- On that figure
- planned campus total per DCD ('2GW'); first phase 250MW, expandable to 500MW
- Operating or planned
- 2025
- Record checked
- Sep 29, 2026
Sources
Everything above comes from these. Open one and check it yourself.
Other projects nearby
Sites we track within 40 km.
Moratoriums covering this site
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| TexasState | Moratorium | Aug 3, 2026 | No end date | Record off site ↗ |