OpenAI Stargate Michigan data center, Saline Township, Michigan
North side of US-12 (Michigan Ave), Saline Township, MI 48176
Related Digital·Under construction·1,383 MW·announced 2025
Related Digital is building the OpenAI Stargate Michigan data center, known locally as "The Barn," on 250 acres in Saline Township, Washtenaw County, for Oracle and OpenAI. Three 550,000-square-foot buildings are under construction, and Related says the campus will deliver over a gigawatt of power, with all three expected online by the end of 2028.
In December 2025 the Michigan Public Service Commission conditionally approved DTE Electric's contracts to supply the 1,383-megawatt data center, run by Oracle subsidiary Green Chile Ventures, and made DTE responsible for any costs it cannot recover from the company. The contracts run at least 19 years and require the data center to pay for at least 80% of its contracted demand even if it uses less.
The township board first voted to deny rezoning the farmland, but Related Digital sued, and the township settled with a consent agreement requiring it to approve the project and a tax exemption. On July 14, 2026, the board approved a 12-year, 50% property tax abatement based on a $4.8 billion valuation, far below the $43 billion Oracle had offered. "Billionaires and greedy politicians are never going to be satisfied," Saline resident Tim Bruneau told the board.
Later that month the board voted 5-0 to remove the cap after the township attorney warned it would violate the 2025 consent judgment and risk damages. Resident Kathryn Haushalter and attorney Ellis Boal then asked the Michigan State Tax Commission, on August 12, 2026, to deny the exemption, arguing the township skipped the public hearing needed to create the industrial development district the tax break depends on.
Boal also pointed to Oracle's exemption application, which lists February 6, 2026, as the start of property improvements. The Michigan State Tax Commission has not yet ruled on the challenge.
The facts on file
- Company
- Related Digital
- Tenant
- Oracle / OpenAI
- Program
- Stargate
- Address
- North side of US-12 (Michigan Ave), Saline Township, MI 48176
- County
- Washtenaw County, Michigan
- Country
- United States
- Status
- Under construction
- Power
- 1,383 MW
- On that figure
- Not yet operating per Epoch AI (satellite/permit tracked)
- Announced
- 2025
- Operating or planned
- 2028
- Record checked
- Sep 16, 2026
Sources
Everything above comes from these. Open one and check it yourself.
- www.related-digital.com/michigan
- epoch.ai/data/ai-data-centers/directory/openai-stargate-michigan
- www.michigan.gov/mpsc/commission/news-releases/2025/12/18/mpsc-approves-dte-electric-energy-contracts-for-data
- www.michiganpublic.org/environment-climate-change/2026-07-15/saline-township-approves-smaller-than-planned-tax
- planetdetroit.org/2026/07/data-center-news-saline-township/
- michiganadvance.com/2026/08/14/in-bid-to-stop-saline-data-center-tax-break-an-attorney-argues-the-township-ski
- epoch.ai/publications/openai-stargate-where-the-us-sites-stand
Other projects nearby
Sites we track within 40 km.
- Thor Equities Data Center21 km
- Project Ironwood (Cloverleaf Infrastructure)22 km
- University of Michigan Los Alamos Data Center30 km
- US Signal Data Centerlisted on the Wayne County page39 km
- Panattoni Project Cannoli40 km
Moratoriums covering this site
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| SalineTown or city | Moratorium | Jan 12, 2026 | Jan 12, 2027 | Record off site ↗ |
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.