Home/United States/Texas/Brazos County/Project Aggie
Project Aggie data center, College Station, Texas
Midtown Business Park, College Station, TX 77802
Priority Power Management·Blocked·600 MW·200 acres·decided Sep 11, 2025
College Station's City Council unanimously rejected the sale of about 200 city-owned acres to Priority Power Management on September 11, 2025, blocking its Project Aggie plan for Midtown Business Park. The proposed site was along Corporate Parkway and Midtown Drive, behind Costco, and the land deal was valued at about $30 million. The developer's conceptual design showed two data-center buildings and two substations, with up to 600 megawatts of power at full buildout; none of that capacity was built.
Residents objected to placing a large industrial campus near homes and to how little time they had to examine the deal. More than 75 people registered to speak at the council meeting, and opponents delivered a petition with 5,047 signatures. They raised noise, water and power concerns, while the city presented a proposed 600- to 900-foot planted buffer and said separate water and power agreements and a sound study would still be needed.
The financial offer was substantial but contested. City officials estimated $10 million to $22 million a year in taxes and electric-fund transfers on top of the land price; their presentation projected 45 permanent jobs. Residents and Midtown developer James Murr questioned whether that was enough employment for 200 acres intended to support the wider business district.
After nearly six hours of public discussion, the council voted down the sale, despite a staff recommendation to approve it. In January 2026, Mayor John Nichols said College Station had begun discussing rules for where future data centers could be placed, but KBTX reported no timetable for those rules. The rejected land agreement did not authorize Project Aggie to proceed on the Midtown site.
The facts on file
- Company
- Priority Power Management
- Address
- Midtown Business Park, College Station, TX 77802
- County
- Brazos County, Texas
- Country
- United States
- Status
- Blocked
- Power
- 600 MW
- Land
- 200 acres
- Reported size
- 200 acres, up to 600 MW
- Site
- Midtown Business Park, Corporate Pkwy and Midtown Dr
Sources
Everything above comes from these. Open one and check it yourself.
- www.datacenterdynamics.com/en/news/college-station-texas-rejects-land-sale-for-data-center/
- www.kbtx.com/2025/09/12/college-station-city-council-unanimously-rejects-land-sale-ai-data-center/
- blog.cstx.gov/wp-content/uploads/2025/09/2-Priority-Power-Real-Estate-Contract.pdf
- www.kbtx.com/2025/09/11/college-station-weighs-data-center-deal-that-could-shift-vision-midtown-district/
- www.kbtx.com/2026/01/15/data-center-pushback-sparks-proactive-regulations-across-texas/
- www.datacenterdynamics.com/en/news/600mw-data-center-campus-proposed-in-texas/
- www.kbtx.com/video/2025/09/12/college-station-city-council-unanimously-rejects-land-sale-ai-data-center/
- theeagle.com/news/local/government-politics/article_3314091f-8c25-4852-bb1b-b9b77681d824.html
Other projects nearby
Sites we track within 40 km.
- Cipher Milsing29 km
Moratoriums covering this site
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| TexasState | Moratorium | Aug 3, 2026 | No end date | Record off site ↗ |
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.