Cielo Digital Infrastructure data center, Kansas City, Missouri
Kansas City, MO
Proposed·500 MW
Cielo Digital Infrastructure, a Texas-owned developer, has named a site on the Missouri side of Kansas City for a data center campus of up to 500 megawatts on 146 acres, but only in a list of planned projects published with its South Carolina announcement, with no address, date or tenant.
Any such campus inside the city would face the rules the Kansas City council passed unanimously in January 2026, the first zoning written there for data centers. Before, developers could build one by right in nearly any part of the city; now data centers under 500,000 square feet need a special use permit, bigger ones fall into a new large format category, and none can go in rural, residential, neighborhood or retail districts without a rezoning or special use permit. Utility providers must also submit a letter saying they can meet a data center's water and energy demand, and final approval of most data centers rests with the council.
The facts on file
- Address
- Kansas City, MO
- County
- Jackson County, Missouri
- Country
- United States
- Status
- Proposed
- Power
- 500 MW
- On that figure
- planned 'up to' figure
- Site location
- Exact parcel not confirmed, so the pin is approximate.
- Record checked
- Sep 29, 2026
Sources
Everything above comes from these. Open one and check it yourself.
Other projects nearby
Sites we track within 40 km.
- Iron Mountain Kansas City (KCM-1)listed on the Jackson County page5 km
- Revitalization Unlimited Data Center10 km
- DataBank Kansas City metro (KC1-KC3)listed on the Johnson County page13 km
- Google Kansas City East18 km
- Nebius Data Center21 km
- Patmos Data Center21 km
- Metrobloks data center23 km
- Project Red Wolf30 km
Moratoriums covering this site
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| Jackson County | Moratorium | Jun 22, 2026 | Dec 19, 2026 | Record off site ↗ |
| Kansas CityTown or city | Zoning limits | Jan 16, 2026 | No end date | Record off site ↗ |
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.