Expedient is not a hyperscale developer or a builder of gigawatt campuses. It sells colocation and managed cloud services from about a dozen data centers across the Midwest and East, most of them in buildings it leases rather than owns.
AMP Capital bought the company in 2019 in a deal reported at more than $500 million. DigitalBridge became its investment manager in 2022 after buying the infrastructure equity business of AMP's subsidiary Collimate Capital for $328 million, a group of holdings that included Expedient.
Ohio is where Expedient has been most active, and where it has started buying rather than renting. In February 2024 it took over a former Nationwide Mutual Insurance data center at 281 E. Powell Road in Lewis Center, north of Columbus: 102,000 square feet built in 1985, with four carriers and 3 megawatts of power to be raised to 7.5 megawatts.
Two years later it exercised a purchase option on 5700 Innovation Drive in Dublin, a 29,210-square-foot building with 4.8 megawatts of power that Five 9s Digital had built for it in 2016; the deal closed in March 2026.
In Franklin, outside Milwaukee, the investment firm StratCap bought Expedient's leased data center in August 2022: a 28,500-square-foot building built originally for Harley-Davidson in 2008, with 1.2 megawatts of critical load that can be doubled.
Expedient sites on record
Grouped by country, then by state or region, biggest first. Open one to see the projects there. The report above may name sites that have no record here yet.
United States13 · 32 MW
Ohio5
| Project | Company | Status | Power | |
|---|---|---|---|---|
| CLE1Cleveland | Expedient | 5 MW | Source off site ↗ | |
| CMH2Dublin | Expedient | 5 MW | Source off site ↗ | |
| CLE2Cleveland | Expedient | 2 MW | Source off site ↗ | |
| CMH1Upper Arlington | Expedient | 1 MW | Source off site ↗ | |
| CMH3Lewis Center | Expedient | Not reported | Source off site ↗ |
Arizona2
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Expedient PHX1Phoenix | Expedient | 4 MW | Source off site ↗ | |
| Expedient Data CenterPhoenix | Expedient | 2 MW | Source off site ↗ |
Pennsylvania2
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Expedient PIT2Pittsburgh | Expedient | 4 MW | Source off site ↗ | |
| Expedient PIT1Pittsburgh | Expedient | 1 MW | Source off site ↗ |
Indiana1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| IND1Carmel | Expedient | 4.4 MW | Source off site ↗ |
Maryland2
| Project | Company | Status | Power | |
|---|---|---|---|---|
| TidepointBaltimore | Expedient | 2 MW | Source off site ↗ | |
| BWI1Owings Mills | Expedient | 0.8 MW | Source off site ↗ |
Wisconsin1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Expedient Milwaukee (MKE1) Data CenterFranklin | Expedient | 1 MW | Source off site ↗ |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.