Global Data Centers.formerly Florida Data Centers

Home/Companies/Crusoe

Data centers by company

Crusoe data centers: 8 sites mapped

8 projects tracked
·
5 proposed or being built
·
1 operating
·
1 stopped or paused
·
1 with no stage on record
·
2,700 MW from the 3 active projects that report a figure
·
2 countries
Crusoe/Blue Energy Data Center (Proposed, 1,500 MW)Crusoe Abilene Expansion (Under construction, 900 MW)OpenAI Stargate Abilene (Operating, expanding, 300 MW)Crusoe Project Flash (Summit View Business Park) (Cancelled, 100 MW)Goodnight (Under construction)Crusoe Alberta (gas-powered) (Not reported)Crusoe Data Center (Proposed)Crusoe Data Center (Approved)
Boundaries: Natural Earth
Tracked projectStopped or pausedBigger dot, more power8 sites shown

Crusoe is expanding its Stargate data center campus in Abilene, Texas, built for Oracle and OpenAI and now also serving Microsoft, to about 2.1 gigawatts of power. The site runs on its own gas power plant, and on August 5, 2026 the Texas Commission on Environmental Quality gave preliminary approval to grow that plant from 10 turbines to 49. State Rep. Stan Lambert asked for a public meeting in Abilene, and the public comment period stays open until that meeting is held.

Neighbors say they were never told. Omaira Garcia, an Air Force veteran who lives about 500 yards from the plant, said she learned of the project only after construction began in 2024. "We weren't given any time to understand what this impact was going to be on us," she told Floodlight, in reporting published by the Texas Tribune. "We're trapped here." Her neighbor Paul Daniel, 81, said, "We were never advised or anything." Crusoe received an 85 percent property tax break on the project, and some homes sit within half a mile of the plant, according to the Texas Observer.

Crusoe also helped start a 1.8 gigawatt campus called Project Jade in Laramie County, Wyoming, approved unanimously by county commissioners on January 6, 2026, but it left the project around April 2026. Its partner Tallgrass, which is building a gas plant next door to power the site, has kept developing it directly with the data center client and says it has grown to 2.7 gigawatts. The Hyndman Homesites Homeowners Association had raised concerns about wells into the aquifer, turbine emissions, noise and wastewater ponds. "You don't know until you punch a hole in it what you're dealing with," the association's president, Randy Fox, said of the groundwater.

Crusoe sites on record

Grouped by country, then by state or region, biggest first. Open one to see the projects there. The report above may name sites that have no record here yet.

United States7 · 2,800 MW
Texas4
ProjectCompanyStatusPower
Crusoe/Blue Energy Data CenterPort LavacaExact site not confirmed Crusoe Proposed 1,500 MW
Crusoe Abilene ExpansionAbilene Crusoe Under construction 900 MW
OpenAI Stargate AbileneAbilene Crusoe Operating, expanding 300 MW
GoodnightClaude Crusoe Under construction Not reported
Virginia1
ProjectCompanyStatusPower
Crusoe Project Flash (Summit View Business Park)Rocky Mount Crusoe Cancelled 100 MW
Missouri2
ProjectCompanyStatusPower
Crusoe Data CenterCallaway CountyExact site not confirmed Crusoe Proposed Not reported
Crusoe Data CenterWarrenton Crusoe Approved Not reported

Every data center in United States

Canada1
Alberta1
ProjectCompanyStatusPower
Crusoe Alberta (gas-powered)Grande Prairie County Crusoe Not reported Not reported Source off site ↗

Every data center in Canada

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.