Global Data Centers.formerly Florida Data Centers

Home/United States/Texas/Navarro County

Data centers by place

Data centers in Navarro County, Texas: 1 project mapped

1 project tracked
·
1 operating
·
400 MW reported
Riot Platforms (Operating, expanding, 400 MW)
Imagery: Esri, Maxar
Tracked projectBigger dot, more power1 site shown

Navarro County's data center story is Riot Platforms, the Colorado bitcoin miner turning itself into an AI landlord. Its campus sits at 6980 FM 709, about seven miles outside Corsicana. The city announced it in April 2022 as the world's largest bitcoin mine, and Riot broke ground that October on a 400-megawatt first phase, cooled by immersing the machines in liquid. ERCOT approved the site for a full gigawatt, and Riot expanded the land to about 890 acres by 2025. In 2026 it filed state paperwork for Project Ditto, a $400 million data center building, with construction running from April 2026 to May 2028.

The fight here was over a tax break. In March 2024 the Commissioners Court took no action on Riot's reinvestment-zone request after Commissioner David Brewer said his office was flooded with calls from residents. Riot had asked to pay half the county's property tax rate for 10 years, saving almost $14 million on a mine county records put at more than $640 million. Riot came back in October 2024 to a standing-room-only meeting, and, weighing its promise to nearly double its workforce to 290, Brewer and two other commissioners approved the abatement, the bare majority needed.

Read more

The objections have been water, power and noise. The unexpanded mine needs just under 1.5 million gallons of water a day, roughly an eighth of Corsicana's maximum daily use. Riot says it is drilling wells into the Woodbine Aquifer and storing rainwater in an 18.5-acre pond. "The people living off of [FM] 709, these beautiful people, were not informed, nor did they consent," said Jackie Sawicky, who founded a local coalition against the mine and disbanded it after the vote. Immersion cooling has so far kept the mine quiet, unlike the fan-cooled MARA mine in Hood County, whose neighbors have sued over the noise.

Riot is now converting its approved power here and at its Rockdale campus for AI tenants, though its big leases so far, including a reported $9.1 billion deal with Anthropic, are at Rockdale rather than Corsicana. The county also has a small AI project at Rice, where EG AI Corp broke ground in June 2026 on a 2.5-megawatt immersion-cooled GPU facility in a converted warehouse, due in 2027.

Data center projects on record in Navarro County

Grouped by the town each site sits in. The report above may name projects that have no record here yet.

Corsicana1
ProjectCompanyStatusPower
Riot PlatformsCorsicana Riot Platforms Operating, expanding 400 MW

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.