Global Data Centers.formerly Florida Data Centers

Home/United States/Oregon/Morrow County

Data centers by place

Data centers in Morrow County, Oregon: 6 projects mapped

6 projects tracked
·
4 proposed or being built
·
2 operating
·
1,340 MW from the 3 active projects that report a figure
AWS Threemile Exascale (Proposed, 1,000 MW)Percheron Data Center (Proposed, 300 MW)AWS Boardman Gar Swanson (Operating, 40 MW)AWS Boardman Olson Road (Operating)AWS Boardman Bombing Range (Under construction)AWS Boardman Tower Road East (Under construction)
Imagery: Esri, Maxar
Tracked projectBigger dot, more power6 sites shown

Morrow County, a farming county in northeastern Oregon, has become a hub for Amazon data centers around Boardman, and the county has courted them. In May 2023 the Port of Morrow approved tax breaks worth an estimated $1 billion for six more Amazon data centers, adding to four already there. "If you want to have people move to your county, if you want your young people to come back... you have to give them jobs," said county commission chair David Sykes. In March 2026 Amazon confirmed it had bought 1,300 acres near Boardman, formerly grazing land; a filing describes 16 to 20 buildings of 250,000 square feet each, about 1,000 megawatts of power and $8 billion to $12 billion of investment.

A seventh company, Rowan Digital Infrastructure, is separately proposing a 300-megawatt data center near Boardman called Project Percheron. The county's data centers have been drawn into its worst environmental problem: at least 634 domestic wells nearby have unsafe levels of nitrate, some at nearly ten times the federal limit, and many of the affected families are low-income and Latino. Nitrogen-rich wastewater the Port of Morrow collects from food processors and data centers, including water used to cool Amazon's servers, is spread on farm fields and adds to the pollution, according to the Oregon Capital Chronicle.

On March 31, 2026 Amazon agreed to pay $20.5 million to settle its part of a lawsuit brought by residents who cannot drink their well water, without admitting fault. "These billion-dollar companies pollute with impunity, without regard for the human cost," said Nella Parks of Oregon Rural Action, which has urged Amazon to slow its expansion and treat its wastewater. The case continues against the Port of Morrow and other defendants.

Data center projects on record in Morrow County

Grouped by the town each site sits in. The report above may name projects that have no record here yet.

Boardman5
ProjectCompanyStatusPower
Percheron Data CenterBoardmanExact site not confirmed Rowan Digital Infrastructure Proposed 300 MW
AWS Boardman Gar SwansonBoardman Amazon Web Services Operating 40 MW
AWS Boardman Bombing RangeBoardman Amazon Web Services Under construction Not reported
AWS Boardman Olson RoadBoardman Amazon Web Services Operating Not reported
AWS Boardman Tower Road EastBoardman Amazon Web Services Under construction Not reported
Morrow County1
ProjectCompanyStatusPower
AWS Threemile ExascaleMorrow CountyExact site not confirmed Amazon Web Services Proposed 1,000 MW

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.