Global Data Centers.formerly Florida Data Centers

Home/Malaysia/Selangor

Data centers by place

Data centers in Selangor: 8 projects mapped

8 projects tracked
·
4 proposed or being built
·
2 operating
·
1 stopped or paused
·
1 with no stage on record
·
621 MW from the 4 active projects that report a figure
Google Elmina Business Park (Under construction, 100 MW)Vantage Cyberjaya (KUL2) (Under construction, 436 MW)Kota Damansara data center (Withdrawn)NEXTDC KL1 Kuala Lumpur (Under construction, 65 MW)NTT Cyberjaya Campus (CBJ1-CBJ6) (Operating, 20 MW)AWS Cyberjaya (Under construction)DayOne Greater Kuala Lumpur (Cyberjaya) (Not reported)Keppel Basis Bay (Cyberjaya) (Operating)
Imagery: Esri, Maxar
Tracked projectStopped or pausedBigger dot, more power8 sites shown

Selangor approved 39 data center projects between 2021 and 2025, and several large ones are being built now. Google said in August 2026 that its $2 billion data center at Elmina Business Park should open within nine months, and Vantage is building its KUL2 campus in Cyberjaya, which it says will offer 436 megawatts of power when complete. On September 8, 2026, Menteri Besar Amirudin Shari said no data center will be approved without guaranteed water and electricity.

Residents in Kota Damansara, Petaling Jaya, stopped one plan this summer. A proposed three-story data center on Jalan Rimba Riang 9/6 in Section 9 drew about 290 formal objections, including one from a coalition of more than 500 households worried about noise, round-the-clock operation, heat and traffic. The developer's consultant withdrew the application on July 28, 2026, to rethink the site, the city council said. "Thank you to all KD people," assemblyman Muhammad Izuan Ahmad Kasim posted.

Water is the main worry. Any project expected to use more than two million liters a day must now file a detailed water study, and developers must lay their own supply pipes and store three days of water on site. The state says Air Selangor has spare capacity and that the Rasau scheme will add 350 million liters a day, rising to 700 million when its first phase is finished.

Projects not tied to an area

Sites whose records name no county. Everything else is on the pages listed above.

Selangor8
ProjectCompanyStatusPower
Vantage Cyberjaya (KUL2) Vantage Data Centers Under construction 436 MW
Google Elmina Business Park Google Under construction 100 MW
NEXTDC KL1 Kuala Lumpur NEXTDC Under construction 65 MW
NTT Cyberjaya Campus (CBJ1-CBJ6) NTT Global Data Centers Operating 20 MW
AWS CyberjayaCyberjaya Amazon Web Services Under construction Not reported
DayOne Greater Kuala Lumpur (Cyberjaya)Exact site not confirmed DayOne Not reported Not reported Source off site ↗
Keppel Basis Bay (Cyberjaya)Cyberjaya Keppel (Keppel DC REIT) Operating Not reported
Kota Damansara data centerPetaling Jaya Not reported Withdrawn Not reported

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Where people here have won

Projects stopped by a vote, pulled by their developer, or blocked in court.

PlaceWhat happenedDateSize
Kota Damansara Withdrawn by the developer Proposal withdrawn after residents objected. Jul 28, 2026 Not reported

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.