Data centers in Clayton County, Georgia: 4 projects mapped
Unincorporated Clayton County has banned new data center applications since September 2025, a pause the county board has extended twice, now running through December 2026. The ban followed two approvals: TA Realty's 180-megawatt data center in Ellenwood, approved in October 2024, and a Digital Realty campus in Forest Park on the former Fort Gillem site. Clayton County also already has one operating data center, Intero Systems in Atlanta.
In June 2025 the county's Development Authority, known as Invest Clayton, gave TA Realty's $959 million project a 10-year property tax break; the authority would not say what it was worth, but county records point to more than $36 million. Eight residents had spoken against the project in 2024 over water use, noise and traffic. "Data centers are such a massive growth industry that there is no reason why state and local governments should provide incentives to this industry," said Kasia Tarczynska of the watchdog group Good Jobs First. The authority's chairman, C. Harrison Braddy, called the deal "a win-win."
The county's ban does not reach its cities. In Lovejoy, Stillwater Development filed in December 2025 to rezone land for a data center campus of up to 1.25 gigawatts, across the road from two schools. After residents and county commissioners objected at meetings through the summer, Lovejoy withdrew the plan in August 2026; the mayor said the developer would pursue housing there instead.
Data center projects on record in Clayton County
Grouped by the town each site sits in. The report above may name projects that have no record here yet.
Atlanta1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Intero SystemsAtlanta | Intero Systems | Not reported |
Ellenwood1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| TA Realty EllenwoodEllenwood | TA Realty | Approved | 180 MW |
Forest Park1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Digital Realty Forest Park (ATL15)Forest Park | Digital Realty | Approved | Not reported |
Lovejoy1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Stillwater Data Center CampusLovejoy | Stillwater Development | Withdrawn | 1,250 MW |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Moratoriums and bans in effect
Pauses on new data centers covering this area.
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| Clayton County | Moratorium | Sep 3, 2025 | Dec 31, 2026 | Record off site ↗ |
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.