Global Data Centers.formerly Florida Data Centers
Where communities won

Data centers that residents stopped.

Projects killed by a vote, pulled by their developer, or blocked in court, plus every town, county, and state that has pressed pause. Each entry links to the news story or record behind it.

Projects stopped

133 data center projects that residents stopped, by a vote, a withdrawal or a court. Sorted newest first within each state. 590 places also have a moratorium or ban in force; the moratorium tab on this page lists them.

United States111
Arizona5
PlaceWhat happenedDateSizeInvestmentSource
Pinal County, south of EloyVermaland (La Osa)Denied Board of Supervisors voted 4-1 against rezoning.August 26, 20263,300 acres, 11 buildings after cutbackNot reportedkjzz.org
Laveen, PhoenixVintage PartnersWithdrawn Phoenix narrowed where data centers could go and city leadership discouraged the project; the developer switched the site to mixed use.March 3, 202663 acresNot reportedazbex.com
ChandlerActive InfrastructureDenied City Council voted 7-0 against the rezoning, despite lobbying by former Sen. Kyrsten Sinema.December 11, 202540 acres, 422,000 sq ft$2.5Beenews.net
TucsonAmazon Web ServicesDenied The city council voted unanimously to stop the annexation after public outcry over water and energy, and Amazon later withdrew as end user.August 6, 2025290 acresNot reportedtucsonspotlight.org
Buckeye area, Maricopa CountyTract (Project Range)Withdrawn Tract withdrew all four applications after opposition from residents and nearby cities.April 18, 2024about 1,000 acres, 5.6 million sq ft$14Bdatacenterdynamics.com
California3
PlaceWhat happenedDateSizeInvestmentSource
Imperial CountySebastian RucciBlocked in court Court overturned the county approval and ordered a full environmental review.September 9, 2026nearly 1 million sq ftNot reportedkpbs.org
El SegundoEight FormWithdrawn The developer withdrew on the spot at the planning commission after three hours of resident opposition.July 9, 202650 MW, 230,780 sq ftNot reporteddatacenterdynamics.com
Mount ShastaDenied The city manager called it dead on arrival over the water rights attached to the site and told the company no the same afternoon.June 22, 2026Not reportedNot reportedijpr.org
Connecticut1
PlaceWhat happenedDateSizeInvestmentSource
WaterfordNE EdgeWithdrawn After a three year campaign the host fee agreement between NE Edge-Waterford and the town ended in default and expired under its own terms.April 15, 2026about 55 acres, 300 MWNot reportedctmirror.org
Delaware1
PlaceWhat happenedDateSizeInvestmentSource
Delaware CityStarwood Digital VenturesDenied State environmental agency ruled it illegal under the Coastal Zone Act on Feb 3, and the state appeals board upheld that unanimously on March 26.March 26, 2026580 acres, 6 million sq ftNot reportedspotlightdelaware.org
Florida4
PlaceWhat happenedDateSizeInvestmentSource
Holder, Citrus CountyDeltona Corp.Withdrawn Deltona withdrew its comprehensive plan amendment and rezoning applications after resident backlash, and the July hearings were cancelled.June 23, 2026about 800 acresNot reportedfox13news.com
Okeechobee CountyIndian River State College (Okee-One)Withdrawn County Commission dropped the land-use change that would have allowed it, the college cancelled, and the state pulled its grant after 3,000+ residents signed a petition.April 23, 2026205 acres, 9-10 MWNot reportedwgcu.org
IndiantownSilver Fox 606 LLCWithdrawn Developer withdrew the proposal after opposition over wetlands and protected species.April 2026606 acres, 2 million sq ftNot reportedwflx.com
St. Lucie County, Minute Maid RdTimberline Real Estate Partners (land owner Epic Estates 68)Withdrawn Planning and zoning voted 4-2 against it, then the developer withdrew amid resident opposition and a new state data center law.February 26, 20261,218 acres, 1 GW, up to 15 million sq ft$13.5Bwptv.com
Georgia6
PlaceWhat happenedDateSizeInvestmentSource
Lovejoy (Stillwater Technology Park)Stillwater DevelopmentWithdrawn The developer withdrew after intense pushback over water use and nearby schools, and plans homes instead.August 2026400 acres, 15 buildings, 1.25 GW$13Bbaxtel.com
Douglas CountyEdgeConneXDenied County Commission voted 4-1 to deny, the second denial on this site in 7 months.July 7, 2026700 acres, 4.4 million sq ftNot reporteddouglascountysentinel.com
FayettevilleCrow Holdings DevelopmentWithdrawn After the planning commission rejected it, the developer dropped its appeal to the city council.March 2026Not reportedNot reportedbaxtel.com
Jones CountyEagleRock Partners (Crooked Creek Technology Park)Withdrawn Developers withdrew the rezoning less than a day before the hearing after residents organized, and the county passed a 90-day moratorium.October 2025634 acres, 1.8 million sq ft$5Bdatacenterdynamics.com
Bolingbroke, Monroe CountyBolingbroke Technology CenterDenied County commissioners voted unanimously against the rezoning after the planning board also said no. Landowners have sued.August 5, 2025970 acres, 9 buildings, 5.4 million sq ft, 1.2 GW$5.8Bdatacenterdynamics.com
Adairsville, Bartow CountyAtlas DevelopmentWithdrawn Withdrawn after the county planning commission recommended denial.May 1, 2025588 acres, 6 buildings, 432 MW$4.5Bajc.com
Idaho1
PlaceWhat happenedDateSizeInvestmentSource
PocatelloLex Developments LLCDenied Hearing examiner denied the permit in May, and City Council upheld the denial 4-1 on July 16.July 16, 202649 acres$2.6Bdatacenterdynamics.com
Illinois5
PlaceWhat happenedDateSizeInvestmentSource
Hoffman EstatesKaris CriticalWithdrawn Plan commission voted 4-2 against; developer withdrew the rezoning.July 1, 2026186 acresNot reportedcapitolnewsillinois.com
PekinWestern Hospitality PartnersWithdrawn The mayor ended the city land deal in March after heavy opposition, and the developer formally withdrew May 5.May 5, 2026321 acresNot reportedwvik.org
RochelleDenied City Council voted 7-0 against it.April 27, 202648 MW first phaseNot reportedmystateline.com
Barrington HillsBrennan Investment GroupWithdrawn Brennan pulled out before its first public presentation after a resident petition, and the village called the matter closed.January 27, 2026about 110 acres$2Bdatacenterdynamics.com
NapervilleKaris CriticalDenied City Council voted 6-1 against it after 5,000+ residents signed a petition.January 20, 202624 MW, 145,000 sq ft, 40 acresNot reporteddatacenterdynamics.com
Indiana4
PlaceWhat happenedDateSizeInvestmentSource
Franklin Township, IndianapolisGoogle (Deep Meadows LLC), Project FloWithdrawn Google pulled its rezoning minutes before the City-County Council was expected to vote it down.September 22, 2025468 acres, 4 buildings$1Bwfyi.org
McCordsville, Hancock CountySurge DevelopmentWithdrawn Surge withdrew the rezoning for more than 700 acres a week before the vote, after opposition over farmland and the orchard next door.May 13, 2025more than 700 acresNot reportedwthr.com
Leesburg, Kosciusko CountyPrologisDenied County commissioners voted 3-0 against the rezoning after a 1,000+ signature petition, and Prologis said it would not look elsewhere in the county.April 22, 2025554 acres$10Binsideindianabusiness.com
ChestertonProvident Realty AdvisorsWithdrawn Developer withdrew after residents organized and the Town Council said it could never support the project.June 10, 2024200 acres, 8 buildings$1.3Binsideindianabusiness.com
Kansas1
PlaceWhat happenedDateSizeInvestmentSource
Spring HillColossus Data Center AdvisorsWithdrawn The developer pulled out before the planning commission meeting after two weeks of opposition from about forty neighbours and the threat of a lawsuit.March 24, 2026316 acresNot reportedkshb.com
Kentucky2
PlaceWhat happenedDateSizeInvestmentSource
Ekron, Meade CountyDenied Planning commission and Fiscal Court both voted unanimously no after 150 people signed up to speak.October 14, 2025138 acresNot reporteddatacenterdynamics.com
La Grange, Oldham CountyProject LincolnWithdrawn The developer withdrew after community opposition, and the county passed a 150-day moratorium.2025267 acres$6 billionwdrb.com
Maine1
PlaceWhat happenedDateSizeInvestmentSource
LewistonMillCompute LLCDenied City Council voted 7-0 against it after residents packed the chamber.December 16, 202585,000 sq ft$300Mmainepublic.org
Maryland1
PlaceWhat happenedDateSizeInvestmentSource
Lusby, Calvert CountyAWSWithdrawn AWS withdrew its site plan after voters ousted pro-data-center commissioners and the county moved toward a moratorium.August 4, 20268 buildings, 2.4 million sq ftNot reporteddatacenterknowledge.com
Michigan6
PlaceWhat happenedDateSizeInvestmentSource
Augusta TownshipThor EquitiesDenied Voters overturned the rezoning by about 90% in a ballot referendum.August 4, 2026522 acres$1Bwemu.org
Allen ParkSolstice DataDenied Planning Commission voted 7-2 to deny the site plan, and the city then passed a moratorium.June 202626 MW, 45,000 sq ftNot reportedplanetdetroit.org
Washington Township (Macomb County)PrologisWithdrawn Prologis withdrew its rezoning after months of protests, and the township moved to a moratorium. Prologis says it may reapply once rules are written.May 19, 2026312 acresNot reportedplanetdetroit.org
LansingDeep GreenWithdrawn Deep Green withdrew its rezoning hours before the City Council vote, and the city later passed a moratorium.April 6, 202624 MW plus a 16 MW fuel cell plantNot reportedmichiganadvance.com
Howell TownshipVan Gilder family land, reportedly for MetaWithdrawn The rezoning was withdrawn the night before the board vote, after a 3,700-signature petition and a township moratorium. Officials say it may come back.December 7, 2025about 1,000 acres$1Bcbsnews.com
Kalkaska CountyRocklocker LLCWithdrawn The developer withdrew after fierce opposition from residents.November 2025Not reportedNot reporteddatacenterdynamics.com
Minnesota4
PlaceWhat happenedDateSizeInvestmentSource
MinneapolisLegacy InvestingWithdrawn Developer withdrew its land use application after neighborhood opposition.September 11, 202620 MWNot reportedmprnews.org
Elk RiverSwervo Development / Elk River CapitalWithdrawn City Council unanimously rejected the zoning change, then the developer withdrew.July 6, 202633 MW, 60,000 sq ftNot reportedmprnews.org
Nobles CountyGeronimo PowerDenied County commissioners voted down the zoning change the project needed on farmland.April 21, 2026959 acres, 2.5 million sq ft, 400 to 450 MW$4Bdatacenterdynamics.com
Apple ValleyOppidan / Rockport LLCDenied City Council unanimously denied the site plan and permits, after rejecting the land-use change it needed in January.March 26, 2026134 acres, 5 buildings, 1.05 million sq ft, 250 to 300 MWNot reporteddatacenterdynamics.com
Mississippi1
PlaceWhat happenedDateSizeInvestmentSource
StarkvilleStarkville Energy LLCDenied The planning and zoning commission denied the exemption, finding the application lacked transparency and had not addressed residents’ concerns.August 11, 202630 MWNot reportedreflector-online.com
Missouri3
PlaceWhat happenedDateSizeInvestmentSource
Kansas CityRevitalization UnlimitedDenied The city plan commission voted 6-0 to reject it after 475 letters, none of them in favour, and 55 people testified.August 5, 202620 storeys, 384 feetNot reportedkcur.org
St. JosephCapstone Technology CampusWithdrawn The landowner withdrew the annexation and rezoning applications himself, a month before the hearing.June 26, 2026400 acresNot reportedkq2.com
Peculiar, Cass CountyDiode Ventures (Harper Road Technology Park)Denied Board of Aldermen removed data centers from the zoning code after residents packed meetings, blocking the project.October 2024508 acres, 7 buildings$1.5Bdatacenterdynamics.com
Montana1
PlaceWhat happenedDateSizeInvestmentSource
Bonner, Missoula CountyKrambuWithdrawn The landowner pulled his signature from the application after months of resident opposition, and the county said the project will not move forward.July 6, 20267 MW to start, up to 100 MWNot reportedmontanafreepress.org
Nevada1
PlaceWhat happenedDateSizeInvestmentSource
Boulder City, Eldorado ValleyTownsite Solar 2 LLCBlocked in court The developer withdrew from the city site after pushback, then won federal approval on nearby federal land. The Interior Department appeals board halted it on Sept 1 after the city and environmental groups appealed.September 1, 202680 acres, 167 MW data center plus 70 MW batteryNot reported8newsnow.com
New Hampshire1
PlaceWhat happenedDateSizeInvestmentSource
NottinghamTom Moulton (Nottingham Business Park LLC)Withdrawn Developer withdrew hours before a packed planning board meeting after a 29,000-signature petition. Voters then passed a one-year moratorium.May 27, 202640 acresNot reporteddatacenterdynamics.com
New Jersey4
PlaceWhat happenedDateSizeInvestmentSource
East Greenwich Township (Mount Royal)American TowerWithdrawn American Tower withdrew after a 5,800-signature petition, and the township then banned future data centers.June 22, 20264 MW, about 16,000 sq ft, 6.2 acresNot reporteddatacenterdynamics.com
Andover Township (former Newton Airport)National Land Developers LLCDenied After weeks of protests the township unanimously banned data centers. The developer is now suing to overturn the ban.June 2026about 97 acresNot reportedgovtech.com
Monroe TownshipHexa BuildersDenied Township officials rejected the proposal. The developer is now suing the township for $300 million.May 20261 million sq ftNot reportedcourierpostonline.com
New BrunswickDenied City Council voted unanimously to remove data centers from the redevelopment plan and build a park instead.February 18, 202627,000 sq ftNot reportedjerseyvindicator.org
New Mexico1
PlaceWhat happenedDateSizeInvestmentSource
SocorroGreen Data, with New Mexico TechWithdrawn New Mexico Tech dropped the project after months of protests, and the county then passed a one-year moratorium.June 2, 202610,000 acres, 2 GWNot reporteddatacenterdynamics.com
North Carolina6
PlaceWhat happenedDateSizeInvestmentSource
Garner, RaleighBeacon PartnersWithdrawn Beacon Partners withdrew the proposal, as the mayor of Raleigh confirmed.August 15, 202613 acresNot reportedwral.com
Rural Hall, Forsyth CountyDrox GroupDenied County commissioners voted 5-2 against rezoning, after the planning board also said no in June.July 30, 2026129 acres, 1.3 million sq ftNot reportedwfae.org
Kingsboro, Edgecombe CountyEnergy Storage SolutionsWithdrawn Developer withdrew after a special-use permit denial and county moratorium debate.July 6, 20261,700 acres, 300 MW$19.2Bbisnow.com
Apex (New Hill)Natelli Investments (New Hill Digital Campus)Withdrawn Natelli withdrew its annexation and rezoning after a 5,000-signature petition, and Apex moved to pause data centers.March 5, 2026250 MW, 189 acres, 6 buildingsNot reportedindyweek.com
MatthewsCrosslandWithdrawn The developers withdrew the rezoning after a petition gathered more than 2,700 signatures; the commissioners accepted the withdrawal and the land keeps its residential zoning.October 8, 2025123 acres, 5 buildingsNot reportedwunc.org
MooresvilleTract (Mooresville Technology Park)Withdrawn Tract fully withdrew its rezoning after 200+ residents and Dale Earnhardt's son Kerry spoke out, weeks before the vote.August 13, 2025400 acres, 1.5 million sq ft$30Bdatacenterdynamics.com
Ohio5
PlaceWhat happenedDateSizeInvestmentSource
PataskalaAligned Data CentersDenied City Council unanimously upheld the planning commission's 5-2 denial.August 25, 2026200 MW$5B+ (company figure)nbc4i.com
AmherstCervenka Development PartnersDenied Board of Zoning Appeals rejected the variance the day after a hearing that drew 100+ residents.July 30, 202645 MW, 240,000 sq ft, 36.6 acresNot reportednews5cleveland.com
ClevelandLakeland Equity GroupDenied City rejected the permit after it failed zoning review, and council then moved to pause new data centers.May 14, 202635 acres, 300,000 sq ft, 150 MW$1.6Bdatacenterdynamics.com
Preble CountyPRSM Land Development GroupWithdrawn Landowners withdrew the rezoning two days before the commissioners vote, after an overflow public hearing. The developer says it may try again.September 29, 2025about 300 acresNot reporteddatacenterdynamics.com
NortonQuantum HPC (Project Triton)Withdrawn The project was cancelled after strong opposition from residents at public meetings.202590 acres, 485,000 sq ft plus a gas turbine power yard$2Bbaxtel.com
Oklahoma1
PlaceWhat happenedDateSizeInvestmentSource
CowetaBeale Infrastructure (Project Atlas)Withdrawn Beale pulled its rezoning after the planning commission recommended denial and residents organized against it.March 30, 2026270 acresNot reportedkosu.org
Oregon3
PlaceWhat happenedDateSizeInvestmentSource
SalemVerrusWithdrawn Governor ordered the state land sale withdrawn.July 30, 202632-75 acres$5Bkatu.com
La PineBoxminer (bitcoin mining)Denied City Council voted unanimously against selling the land after hours of public opposition.May 27, 202620 MW, 19.5 acresNot reportedopb.org
Cascade LocksWithdrawn The port and developer ended the data center deal after community opposition.July 2023Not reportedNot reportedportofcascadelocks.gov
Pennsylvania8
PlaceWhat happenedDateSizeInvestmentSource
Upper Merion Township (King of Prussia)MLP Ventures (Brian O'Neill)Denied Board of Supervisors unanimously denied all five sites. The developer is suing.August 13, 20264.6 million sq ftNot reported6abc.com
East Vincent TownshipPennhurst Holdings LLCDenied Board of Supervisors unanimously denied the conditional use, developer says it will appeal in court.May 21, 20261.9 million sq ft, 125 acresNot reportedchestnuthilllocal.com
South Annville TownshipInch & Co. / Eastern Land & ResourcesWithdrawn The developer withdrew its rezoning after the planning commission voted against it and residents organized protests.May 12, 202699 acres, 5 buildings, about 640,000 sq ft$1.7Blebtown.com
Columbia BoroughSaadia Holding LLCDenied Borough council rejected the land bid for a data center.May 2026Not reportedNot reportedlancasteronline.com
Montour CountyTalen EnergyDenied County commissioners voted 3-0 to deny the rezoning.February 10, 2026800+ acresNot reportedinsideclimatenews.org
Plymouth TownshipO'Neill PropertiesWithdrawn The township planning board unanimously refused to recommend it in October, and the applicant withdrew at the zoning hearing board the following month.November 18, 202566 acresNot reportedinquirer.com
Hazle Township, Luzerne CountyNorthPoint Development (Project Hazelnut), reportedly for AWSDenied Supervisors voted 3-0 to deny the land plans after 200+ residents packed the meeting, and a judge threw out NorthPoint's appeal in May 2026.November 14, 2025about 1,282 acres, 15 buildingsNot reportedfoodandwaterwatch.org
Blakely, Lackawanna CountyWithdrawn The developer withdrew its plans after large crowds turned out against it.September 2025Not reportedNot reporteddatacenterwatch.substack.com
Pennyslvania1
PlaceWhat happenedDateSizeInvestmentSource
Upper MacungieAir Products and ChemicalsDenied Zoning Hearing Board denied it in May, and Air Products let the appeal deadline pass, ending the project.August 5, 2026194 acres, 3 buildings, 2.6 million sq ftNot reportedlehighvalleypublicmedia.org
South Carolina4
PlaceWhat happenedDateSizeInvestmentSource
Spartanburg CountyLighthouse Data Centers / Jones Road AssociatesDenied County staff denied it in June, and the Board of Zoning Appeals unanimously upheld the denial on Aug 25.August 25, 202660 MW, 200,000 sq ftNot reportedwspa.com
Marion CountyStream Data Centers (Project Liberty)Withdrawn Stream cancelled it, citing delays getting power, after months of resident protests over the council approving it in secret.June 11, 2026about 407 acres, 3 buildings, 2 million sq ft$2.4Bwistv.com
Spartanburg County (Tyger River Industrial Park)TigerDC (Project Spero)Withdrawn TigerDC pulled out hours before the county council voted down its tax break after weeks of public opposition.February 27, 2026100 MW first phase$3Bdatacenterdynamics.com
Camden, Kershaw CountyTerra Nexus VenturesWithdrawn The company’s lawyer filed a one sentence withdrawal before the county council could vote, after the planning commission had already approved it.September 15, 2025162 acresNot reportedpostandcourier.com
Texas7
PlaceWhat happenedDateSizeInvestmentSource
BrownsvilleRandr VenturesWithdrawn The applicant withdrew the day before the city met to consider a 90 day moratorium on new data centers.August 5, 2026Not reportedNot reporteddatacenterdynamics.com
Henderson County (Cedar Creek Lake)Diode VenturesWithdrawn Diode pulled out after residents fought its plan to draw lake water, and Gov. Abbott said it failed the state's new standards.July 23, 2026Not reportedNot reportedkeranews.org
TylerVulcan Core LLCDenied The planning and zoning commission refused the special use permit 5-2 after 26 residents spoke against it and the meeting ran three and a half hours.July 7, 20261.8 acres, 12 MWNot reportedtylerpaper.com
KilleenOnmineWithdrawn Planning and Zoning recommended denial 4-1 on April 27, then the applicant withdrew before the June 2 council vote.May 20262.6 acres$30Mkdhnews.com
HuttoZydeco DevelopmentWithdrawn Zydeco withdrew its rezoning after city staff recommended denial and neighbors filed formal protests.April 17, 202670 MW, 40 acresNot reportedkut.org
San MarcosHighlander SM One LLCDenied City Council voted 5-2 to deny the rezoning; the city later banned data centers in every zone (June 16).March 2026200 acres$1.5Bkxan.com
College StationPriority Power (Project Aggie)Denied City Council voted unanimously against selling the land after a 5,000-signature petition and nearly 80 speakers.September 11, 2025200 acres, up to 600 MWNot reportedkbtx.com
Utah1
PlaceWhat happenedDateSizeInvestmentSource
ProvoB+F Timpanogos Tech CenterDenied City Council voted 7-0 against the rezoning, then capped data centers at 50 MW citywide.March 10, 202666,000 sq ft, 5 MW (up to 50 MW)Not reportedheraldextra.com
Virginia12
PlaceWhat happenedDateSizeInvestmentSource
FredericksburgPenzanceDenied The city council voted the project down twice over in the early hours of the morning.August 26, 2026Not reportedNot reportedfredericksburgfreepress.com
Rocky Mount, Franklin CountyCrusoeWithdrawn The data center proposed for Summit View Business Park will not be built.August 17, 2026150 acres, 100 MWNot reportedwdbj7.com
Prince William CountySanders Lane Assemblage I LLCDenied Board of Supervisors voted 8-0 to deny after a five-hour hearing.July 7, 2026about 1,940 acres, 43 million sq ftNot reportedinsidenova.com
Prince William CountyQTS / CompassWithdrawn Courts voided the approvals (appeal court March 31); Compass withdrew April 29; QTS ended the project July 2.July 2, 2026about 2,100 acres, 27 million sq ftabout $25Bvirginiamercury.com
Hanover CountyTractDenied by a vote Board of Supervisors voted 4-3 to deny, even after planners recommended approval.May 27, 2026about 430 acres, 900 MWNot reportedrichmondbizsense.com
Ashland, Hanover CountyLS PowerWithdrawn LS Power pulled its zoning request in a letter from its attorney to the county.May 1, 2026205 acresNot reportedrichmondbizsense.com
Hanover County, near WyndhamHHHuntWithdrawn Planning Commission voted against it, then HHHunt withdrew.January 28, 2026about 400 acres, 10 buildingsNot reportedvpm.org
Louisa CountyAmazon Web ServicesWithdrawn AWS pulled its permit application after strong resident opposition. AWS later bought nearly 2,000 acres in the county, so it could return.July 23, 20257.2 million sq ft$1Bvirginiamercury.com
Pittsylvania CountyBalico LLCDenied Board of Supervisors voted 6-1 against the rezoning for a data center campus and a 3,500 MW gas plant, after refusing Balico's third request to delay.April 15, 2025750 acres, 3,500 MW gas plantNot reporteddatacenterdynamics.com
Charles City CountyDiode Ventures (Roxbury Technology Park)Withdrawn Diode dropped the plan after supervisors delayed their vote in the face of local opposition.2025515 acresNot reporteddatacenterdynamics.com
Catlett, Fauquier CountyHeadwaters Site DevelopmentWithdrawn Developer withdrew its rezoning days before the planning commission hearing amid resident opposition.July 15, 202467 acres, up to 1.4 million sq ftNot reportedfauquiernow.com
Ruther Glen, Caroline CountyVALCODenied The board of supervisors voted 5-1 to refuse the comprehensive plan amendment the campus needed, and VALCO withdrew the rezoning.June 18, 2024855 acresNot reportedfredericksburgfreepress.com
Wisconsin6
PlaceWhat happenedDateSizeInvestmentSource
MilwaukeeTrent OverhueWithdrawn The developer dropped the computing facility from the redevelopment after a plan commission hearing that ran more than six hours.July 6, 2026about 19,000 sq ftNot reportedurbanmilwaukee.com
Cassville, Grant CountyDenied The town rejected the zoning change the project needed and the deal fell apart; the developers had never given their names.April 1, 2026500 acres, 400 MW$2Bwisconsinwatch.org
DeForest, Dane CountyQTS Data CentersWithdrawn The village declared the project not feasible and QTS pulled out after months of resident opposition.February 3, 2026650 acres, 5 buildings$12Bwpr.org
Greenleaf, Brown CountyCloverleaf InfrastructureWithdrawn Cloverleaf dropped its offer to buy land for a data center after an outcry from residents.January 2026Not reportedNot reportedwisconsinwatch.org
Carlton, Kewaunee CountyCloverleaf InfrastructureWithdrawn Cloverleaf gave up on buying the land after the town made plain that it did not want a data center.December 1, 2025800 acres, 100 MWNot reportedpbswisconsin.org
CaledoniaMicrosoft (Project Nova)Withdrawn Microsoft dropped the site after a 2,000-signature petition, days before the village board vote.October 8, 2025244 acres, 3 buildingsNot reporteddatacenterdynamics.com
Australia2
New South Wales1
PlaceWhat happenedDateSizeInvestmentSource
North Katoomba, Blue MountainsMAK Urban GroupWithdrawn Developer withdrew its application after resident petitions and council opposition (next to homes, a school and a creek).June 25, 20263,118 sqm, 1-2 MWA$4.8Mdatacenterdynamics.com
Western Australia1
PlaceWhat happenedDateSizeInvestmentSource
Hazelmere, City of SwanGreenSquareDCWithdrawn Developer withdrew its application after local opposition.May 2026120 MWA$1.1Bechonewspaper.com.au
Canada3
Alberta2
PlaceWhat happenedDateSizeInvestmentSource
OldsSynapse Real Estate CorpWithdrawn Alberta Utilities Commission rejected the gas power plant the campus depended on, calling the site unsuitable.August 17, 20261.4 GWabout $10Bcbc.ca
Rocky View County (near Balzac)KineticorDenied County council voted 6-1 against the plan the campus needed, citing its impact on local farmers.September 9, 20251,107 acresNot reportedcontent.goldenwestapps.com
Ontario1
PlaceWhat happenedDateSizeInvestmentSource
Armour TownshipAlmaguin Data Inc.Withdrawn Developer dropped the project after a petition of 1,000+ residents and required impact studies.June 1, 20262 MW (up to 10 MW), 6.8 acresNot reportedmuskokaradio.com
Chile1
Santiago Metropolitan1
PlaceWhat happenedDateSizeInvestmentSource
CerrillosGoogleBlocked in court Environmental court ruled against it over water use; Google dropped the original design.September 17, 202423 ha$200Melciudadano.com
France2
Auvergne-Rhone-Alpes1
PlaceWhat happenedDateSizeInvestmentSource
AlixanSesterceBlocked in court Administrative court suspended the project.July 10, 202640 MW€1.5Bgrenoble.tribunal-administratif.fr
Ile-de-France1
PlaceWhat happenedDateSizeInvestmentSource
Le BourgetSegroBlocked in court Project blocked; court refused to revive it.July 28, 202625,000 sqmNot reportedactu.fr
Germany3
Hesse2
PlaceWhat happenedDateSizeInvestmentSource
BabenhausenSTACK InfrastructureWithdrawn STACK pulled out after the city council coalition demanded renewable power, noise caps, a water plan and a €250M guarantee, citing a long, uncertain approval process.July 2026270,000 sqm€3Bdatacenterdynamics.com
Gross-GerauVantage Data CentersDenied Town refused permission.February 3, 2026174 MW€2.5Bdatacenterdynamics.com
Thuringia1
PlaceWhat happenedDateSizeInvestmentSource
EisenachDenied City council voted to stop it.July 1, 202680 hectaresNot reportedmdr.de
Ireland4
Dublin2
PlaceWhat happenedDateSizeInvestmentSource
ClondalkinVantage Data CentresDenied National planning appeals board refused permission.April 4, 2025Not reportedNot reportedpleanala.ie
Profile Park, ClondalkinDigital Netherlands VIII B.V.Denied National planning appeals board refused permission for two data centers.February 14, 2024Not reportedNot reportedpleanala.ie
Galway1
PlaceWhat happenedDateSizeInvestmentSource
AthenryAppleWithdrawn Apple dropped the project after years of legal challenges brought by local residents.May 10, 2018about 500 acres€850Mirishtimes.com
Mayo1
PlaceWhat happenedDateSizeInvestmentSource
KillalaMayo Data Hub Ltd (Avaio Digital)Denied National planning appeals board refused permission, citing climate policy.September 17, 202650 MW€1.5Bpleanala.ie
Italy1
Lombardy1
PlaceWhat happenedDateSizeInvestmentSource
TravagliatoEast Gate / Edge GateWithdrawn Developer withdrew its plans.September 2026120 MWNot reportedidcnova.com
Malaysia1
Selangor1
PlaceWhat happenedDateSizeInvestmentSource
Kota DamansaraWithdrawn Proposal withdrawn after residents objected.July 28, 2026Not reportedNot reportedmediaselangor.com
Netherlands2
Flevoland1
PlaceWhat happenedDateSizeInvestmentSource
ZeewoldeMetaWithdrawn Meta abandoned Europe's largest planned campus after the town voted its backers out and the national government refused to sell the land. The Council of State then struck down the zoning in 2023.July 1, 2022166 hectares (410 acres), 200 MWNot reportednltimes.nl
North Holland1
PlaceWhat happenedDateSizeInvestmentSource
HaarlemmermeerGoodmanBlocked in court Court blocked the data center.April 29, 202670 MVANot reportedarticle19.org
United Kingdom3
England1
PlaceWhat happenedDateSizeInvestmentSource
Iver, BuckinghamshireGreystokeBlocked in court UK government admitted in court that its approval was unlawful after a legal challenge.January 22, 202690 MW£1bnfoxglove.org.uk
Scotland1
PlaceWhat happenedDateSizeInvestmentSource
EdinburghShelborn Drummond LtdDenied Council refused the plan unanimously.February 9, 2026210 MWNot reporteddatacentrereview.com
Wales1
PlaceWhat happenedDateSizeInvestmentSource
Amlwch, AngleseyCarbon3.ai LtdDenied Planning application refused over harm to residents and the environment.April 20, 202661 acresNot reportednation.cymru