Data centers in Denmark: 11 projects mapped
Denmark's power grid is full, and data centers are being pushed to the back of the line. On March 2, 2026, the state grid operator Energinet stopped signing new large connections after requests reached 60 gigawatts, against national peak demand of just over 7 gigawatts. Emergency legislation introduced on August 20 would give households, small businesses and green-energy projects first call on the grid and put data centers last. Parliament is reviewing it, and the rules are meant to apply when grid requests are next assessed this autumn.
The biggest new plan is Data Center Kassø, on 105 hectares of farmland at Kassøvej 26, about 15 kilometers west of Aabenraa and 2 kilometers from the village of Hjordkær. The applicant, Dapsi International ApS, plans four large buildings over about six years, with up to 185 backup diesel generators and about 400 staff. Aabenraa municipality set the scope of its environmental review on April 27, 2026; an environmental report, a draft permit and a public hearing come next.
Google bought land beside the Kassø substation, where the Danish and German grids meet, in 2017. Denmark's operating data centers include Google's in Fredericia, Meta's in Odense, Apple's in Viborg and Microsoft's around Køge. Climate and Energy Minister Samira Nawa has blamed "foreign datacentres," especially those of "American tech giants," for the strain on the grid.
Every region we track
Projects on record, place by place
Open a place to see what is proposed, being built, running or stopped there. The report above may name projects that have no record here yet.
Region of Southern Denmark5
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Prime Esbjerg (ESB01)Esbjerg | Prime Data Centers | Proposed | 550 MW | |
| atNorth DEN02 (Varde) | atNorth (CPP Investments / Equinix) | Proposed | 250 MW | |
| Bulk DK01 Campus (Esbjerg, Denmark) | Bulk Infrastructure | Not reported | ||
| Google Aabenraa | Proposed | Not reported | ||
| Google Fredericia | Not reported |
Capital Region of Denmark2
| Project | Company | Status | Power | |
|---|---|---|---|---|
| atNorth DEN01 (Copenhagen) | atNorth (CPP Investments / Equinix) | 30 MW | ||
| Digital Realty Copenhagen Ballerup | Digital Realty | Not reported | Source off site ↗ |
Central Denmark Region1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Apple ViborgExact site not confirmed | Apple | Not reported |
North Denmark Region1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Prime Sæby (Denmark)Saeby | Prime Data Centers | Not reported | 124 MW | Source off site ↗ |
Region Zealand1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Microsoft Køge (CPH03)Koge | Microsoft | Not reported |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.